The Major Works included in the Project are as following:
Civil Works
Site survey / soil investigation, Site preparation, Foundation works, Building
structures including MV & LV Switchgear Building, Fuel Management Shed training
Building, Switchgear room, control room, hydrogen plant building, Fuel forwarding
shed, Cable trench / duct banks/pipe trench, Asphalt Roads, Permanent Fence
Miscellaneous civil works.
Electrical Works
GT-Generator auxiliary systems (by GE), 4 x 18/380kV GSU Power Transformer (by
GE), Protection and Control System, 18/4.16kV Aux. Transformers (by GE), MV & LV
switchgears, MV & LV power cables and control cables, DC system and Inverter,
Earthing System, Indoor / outdoor Lighting and other miscellaneous electrical works
4.16/0.480 kV Aux. Transformers, ISO phase Bus Duct (by GE).
Mechanical Works
4 x 121 MW Gas Turbine generating unit, Fuel system including, Diesel oil
forwarding & filtering skids, Pipe works & valves,, compressed air system, Fire
fightingsystem including piping, valves, hose cabinets and water deluge system,
Water supply system, HVAC system, Water treatment system, Oil bath heater,
Overhead traveling crane and hoist, Exhaust stack and Drainage pump.
|