Arar Generation Expansion  


[Photogallery]


Scope of Work

Supply and Installation of 2 X 60.16 MW Gas Turbine generating sets at ARAR with all associated systems. The scope of work includes the design, engineering, manufacturing, supply, construction, erection, testing and commissioning.


Project Goals

To extend the generation capacity of Arar Power Plant using 2 X 60.16 MW GE gas turbine-generator (GTG) units.


Project Data

Date of Signing of Contract : 29/05/04
Technical Completion : 30/06/06
Preliminary Acceptance : 31/07/06
Final Acceptance : 30/11/06

Major Equipments And Works

• GTG: 2X60.16MW units.
• Fuel System with 4X3750meter cube, tanks.
• Fire fighting and detection system.
• HVAC System.
• 2X110 MVA 132/13.8kV GSU Power transformer.
• Replacement of 2X50MVA GSU transformer of 13.8/33kV with 13.8/132kV transformer of 2 GTs (Unit#5
   & Unit #6) including all protection modifications.
• Auxiliary and BOP transformers and associated MV/LV switchgears.
• Protection and control system: Interfacing with existing system.
• GT-generator unit motor control centers.
• DC Systems: Batteries, battery chargers, UPS system, and interfacing with existing systems.
• 132kV & 13.8kV XLPE cable system and its terminations.
• LV cabling system (for Power, Control, etc.)
• Cable Trays, trenches, etc.
• Earthing System, including extension and interfacing of new addition to the existing system.
• Civil work including foundations, building and all other needed civil works.